Compare MOQ, price and lead time on a like-for-like basis, starting from a shared scope rather than the headline numbers. Give each supplier the same specification revision, colour mix, packaging, testing requirements and delivery destination, then ask them to state assumptions and exclusions in writing.

Which programme and minimum quantity are you comparing?

Separate stock orders, branded variations and new tooling programmes. For stock, confirm available quantities, reservation conditions and any remaining labelling or packing work. A branded variation changes an existing product's branding, colour or packaging; ask whether samples or production preparation are needed. New tooling means making production tools for a new or changed design. Separate development, trial samples and approval stages, and agree tooling ownership, access and maintenance charges rather than assuming them.

MOQ means minimum order quantity: the smallest order the supplier accepts on a stated basis. Confirm whether it applies to the whole order, each variant or each colour. Establish whether quantities mean individual items, sets or cartons, and whether colours can be combined to meet the minimum.

Keep forecast demand separate from committed purchases. If you want staged deliveries, confirm the total purchasing commitment, minimum quantity per release, and who pays for and holds remaining stock. A minimum tied to a total commitment is not the same as a minimum for an independently placed order.

Simple existing products, such as standard floor mats and dash mats, usually carry the lowest minimums. Tooling-intensive ranges such as ute tub liners sit at the other end.

What does the quoted price actually include?

Ask for the currency, quote validity, payment milestones and GST basis. GST is goods and services tax. The ACCC explains that prices displayed only to other businesses do not have to include GST, so never assume a business quote is tax-inclusive.[2]

Request a breakdown identifying tooling, samples and sample freight, packaging, testing, freight and GST as included, separately charged or excluded. Identify which additional charges are fixed and which are estimates. Confirm what work each line covers, particularly sample revisions and testing scope.

Unit price is the amount charged per agreed item or set. Landed cost is the combined cost of getting the goods to the agreed destination. Build that comparison using the applicable freight, insurance, customs clearance, duty and local delivery charges. Confirm who arranges and pays for each component. Do not add costs already included in the unit price.

Show one-off development charges separately. If allocating them across units for budgeting, use the agreed order quantity rather than uncommitted future sales. Compare the initial-order budget separately from repeat-order costs.

Keep cash payable, including applicable GST, separate from net cost after eligible GST credits. For imports, the ATO sets conditions for credits, including GST registration, a creditable purpose and supporting import documentation.[3] Ask your accountant to confirm the treatment; a potential credit is not an automatic reduction in the amount initially payable.

Which dates depend on which approvals?

Lead time is the time between an agreed starting event and an agreed finishing event. “Production lead time” does not necessarily end with receipt at your warehouse.

Request a staged schedule covering the applicable specification freeze, sample approval, production release, completion, dispatch and delivery milestones. Specification freeze means agreeing the version to manufacture. For each stage, record the responsible party, starting condition and target date. Confirm whether “delivery” means leaving the factory, arriving at port or reaching your nominated warehouse.

Identify dependencies such as approved artwork, sample acceptance, agreed payments and required testing. Ask what happens to the schedule if an approval or input arrives late. Update affected dates rather than treating the original estimate as unchanged. Supplier-specific dates need confirmation for the actual programme; general government guidance cannot establish them.

How should changes be agreed before you commit?

Changing a colour, material, pack format or testing requirement can alter the basis of the quote. A contract variation is a change to an existing contract. General contract-drafting guidance from business.gov.au recommends recording agreed variations in writing, including their impact on scope, cost and timing.[1]

Agree a process for both parties to approve changes. Record the revised specification, MOQ implications, additional charges and replacement dates before authorising changed work.

Buyer checklist

  • Confirm the same programme type and specification revision.
  • Define MOQ units, variant and colour rules.
  • Separate one-off charges, unit costs, landed costs and GST.
  • Record milestone dates, approval responsibilities and delivery destination.
  • Obtain written agreement on scope, cost and date changes.

FAQs

Is the lowest unit price the cheapest option? Not necessarily. Compare the initial-order budget, including separate charges and delivery costs, on the same GST basis.

Can a repeat order use the original quote? Do not assume so. Reconfirm specifications, quantity mix, packaging, testing and the applicable commercial terms.

Contact Southern Oasis with your intended scope to discuss a comparable quotation basis.

General information only, not legal or tax advice or a price, MOQ or delivery guarantee. Actual commercial terms must be agreed by both parties.

Sources

[1] business.gov.au — Prepare a contract[2] ACCC — Price displays[3] ATO — GST and imported goods

Links were checked when this guide was reviewed. They are provided for reference and do not constitute endorsement.